Saab 9-5 + Saab 9-5 Cars + Governing bodies and operation receptions + Settings and routine maintenance of the car - Engine General information and preparatory operations Check of kompressionny pressure Engine check by means of the vacuum gage + Repair of 4-cylinder petrol engines + Repair of 6-cylinder petrol engines - Repair of 6-cylinder diesel engines Removal and installation of heads of cylinders and driving belts Removal and installation of a back cover of a belt of a drive of GRM Check of klapanny gaps Removal and installation of pallets of a case Check of pressure of impellent oil Removal and installation of the power unit + Systems of cooling of the engine, heating, ventilation and air conditioning + the Power supply system and production of the fulfilled gases + Systems of electric equipment of the engine + Manual box of gear shifting + Automatic transmission + Coupling and power shafts + Brake system + Suspension bracket and steering + Body + Onboard electric equipment
|
Repair of 6-cylinder diesel engines
Removal and installation of heads of cylinders and driving belts
Removal
|
- Uncover a broad tank of system of cooling.
- Remove from a turbokompressor the inlet pipeline together with the MAF sensor.
- Remove the top cover of the engine.
- Remove the storage battery, give fixture of the assembly block of safety locks and shift it aside.
- Remove the holder of the battery.
- To Poddomkratta the car also remove the bottom protective casing of an impellent compartment.
|
- Weaken a tension of a belt of a drive of auxiliary units and remove it. Then slightly give a back bolt of fastening of the generator. Mark the direction of movement of a belt if its further use is supposed.
|
- Empty system of cooling of the engine.
- Cut a coupler of electroconducting of the sensor of level of impellent oil.
- Turn out a forward bolt of a forward support of the power unit (10 on an illustration).
|
Bolt (10) fastenings of a forward support and delivery tube of a turbokompressor (11).
|
- Disconnect a delivery tube of a turbokompressor from an interkuler (11 on an illustration).
- Turn out bolts of fastening of an arm of an exhaust pipe and give nuts on a joint of an exhaust pipe.
- Remove a delivery hose with a tube from the top inlet pipeline.
- Remove the catalytic converter.
- Cut a coupler on a hose of a radiator and remove the top hose of a radiator.
- Remove the socket and a coupler with directing щупа level of impellent oil. Remove the directing.
- Turn out the top bolt of an elevating eye and weaken the bottom bolt. Take an elevating eye aside.
- Separate sockets, cut a cable coupler and remove a casing of fans of system of cooling.
- Turn out the bottom screw and remove an elevating eye.
|
- Give a nut of a back support of the power unit.
|
|
- Weaken quick disconnect connections of fuel lines (22 on an illustration). Wipe the flowed-out fuel rags.
|
- Unload an engine support, having propped up it a jack. Remove the right support of the engine with top an arm and a pillow. Lift the engine a little more to get access of a bolt of fastening of an arm (23 on an illustration).
|
- Uncover a belt of a drive of GRM.
|
|
- Establish the piston of the first cylinder in the provision VMT of the end of a step of compression. For this purpose combine labels on a pulley of a cranked shaft and on camshaft and TNVD cogwheels with marks in the engine. If labels on a belt not accurate, put them anew.
|
- Unload a roller of a natyazhitel (to the right of a cranked shaft), having turned it and having inserted into an opening in it a core in diameter of 6 mm. Turn out a bolt of fastening of a roller, at the same time extending it on itself.
- Remove a belt of a drive of GRM and an intermediate roller (over cranked shaft).
|
- Remove the pump GUR with an arm.
|
|
- Separate sockets of electroconducting of the engine and clean it aside (30 on сопр. illustrations).
|
- Remove the top section of the inlet pipeline and a turbokompressor arm (31 on an illustration).
- Remove the turbokompressor thermofilter (32 on an illustration).
|
- Remove a clamp and disconnect an operating rod of a vacuum box of a turbokompressor (33 and 34 on an illustration).
|
- Disconnect a vacuum hose (35 on an illustration) and separate the socket (36).
- Disconnect from a turbokompressor submitting tube (37 on an illustration).
|
- Disconnect oil and water tubes, and also the vacuum block from a turbokompressor. Remove a turbokompressor.
|
|
- Remove fuel tubes and the distributive highway.
|
- Remove thermofilters over a final collector. Lower a jack to remove the back thermofilter.
- Remove a pipe connecting blocks of cylinders.
- Disconnect from a cover of a head of cylinders a tube of system of cooling of the engine.
- Remove hoses of ventilation of a case.
- Disconnect the returnable fuel line from forward and back blocks of cylinders.
- Disconnect submitting tubes and remove holders of submitting and returnable fuel tubes from a back head of cylinders.
- Remove covers of heads of cylinders.
|
- Weaken quick disconnect connections in a back part of a bed of a camshaft then remove arms of nozzles (48 on an illustration).
|
- Remove nozzles and returnable fuel lines (49 on an illustration).
|
- Turn out bolts of fastening of covers of cogwheels and a bolt under a cover of a forward number of cylinders (50 on an illustration).
|
- Turn out the hairpins holding arms of nozzles (51 on an illustration).
- Remove hoses of the vacuum pump both back and a lobby of a bed of camshafts.
|
- Turn out bolts of fastening of the EGR valve to a tube of system of cooling (53 on an illustration) and clean knot aside.
|
- Turn out a bolt of fastening of a tube of ventilation of a case to the inlet pipeline of a forward number of cylinders (54 on an illustration).
- Turn out bolts of fastening of a tube of system of cooling to a head of cylinders (55 on an illustration).
- Remove the cable channel of the forward inlet pipeline (56 on an illustration).
- Remove hoses of system of cooling from the back block of cylinders.
- Turn out a bolt of the top fastening of the generator.
|
- Remove heads of cylinders from blocks of cylinders together with final collectors and inlet pipelines.
|
|
|
Installation
|
- Clear interfaced surfaces and combustion chambers. Blow carving openings under bolts of fastening of heads of cylinders the compressed air to remove from them oil and dirt.
- Make sure that the directing are established in blocks of cylinders.
- Establish heads of cylinders with new laying and bolts.
|
Pay attention that bolts have various length, roll them in the corresponding openings. Make sure that laying is laid on the corresponding blocks of cylinders (on laying labels of "L" – left are put, - and «R» – right). The thickness of laying gets out according to Specifications. |
- Tighten bolts of fastening of heads of cylinders in sequence, return specified illustrations item 54 (Removal) and with demanded efforts (see. Specifications).
- Further installation is made in sequence, return to an order of dismantle of components. Pay attention to the next moments:
- Tighten fixture according to requirements of Specifications;
- Use a new submitting tube of TNVD;
- Use new consolidations of nozzles;
- At installation of a cover of a head of cylinders use new laying, and also put hermetic (No. 87 81 841 according to the Saab catalog) on surfaces;
- At installation of the pipe connecting blocks of cylinders, use new laying and grease fixing bolts with means of Molycote 1000;
- Grease with means of Molycote 1000 fixture of a turbokompressor, an arm of an exhaust pipe and its connection;
- Before installation of a belt of a drive of GRM make sure that labels on cogwheels and on a pulley of a cranked shaft are combined with labels on the engine. After installation of a belt turn the engine on 2 complete revolutions and again make sure that adjusting labels of VMT coincide.
- Upon termination of installation fill system of cooling and greasing system. Start the engine and check it on leakages of oil and cooling liquid.
|
|
|
|